Current condition
For each trial, retain blank supplier and batch, board/storage condition, case format, settings, bottom-closure consumables, line demand and the accepted or failed case result.

Agree carton erector trials using real blanks, finished-case checks, accepted output, replenishment, changeover and recovery from incomplete erection.
Use production blanks across the agreed format and board range. Assess case squareness, the loading aperture, flap closure, bottom seal and stable discharge; count accepted cases at loading while including replenishment, rejected blanks, downstream pauses and format recovery.
Follow the five-stage erecting sequence and keep the blank-condition record with the format and restored-setting record. Agree the response to incomplete opening or closure before accepting the result.
Plan carton erecting machines around your product, pack range, target output, cleaning needs and finished-pack checks. Discuss a practical line concept with Lancing using representative samples. Use this guide to resolve finished-pack checks and reject handling before it limits the final system.
Discuss your application

For each trial, retain blank supplier and batch, board/storage condition, case format, settings, bottom-closure consumables, line demand and the accepted or failed case result.
For Carton Erecting Machines, include normal production conditions, credible extremes, product or part variants and changes over time.
Record the stage creating a failed opening, twisted case, incomplete closure or unstable transfer. Agree handling and recovery, and verify the first acceptable case after settings are restored.
Run intended-supplier blanks in ordinary production condition, including board/storage variation, curl, damaged edges and inconsistent folding.
Identify flat-blank drawings and assembled dimensions for each tested format. Include smallest and largest cases and the required loading orientation.
Check squareness, usable loading aperture, flap closure and bottom seal against the reference case. Assess the base with intended contents and onward handling.
Count accepted cases at loading through the agreed production pattern, including replenishment, rejected blanks, buffer behaviour and downstream pauses.
Trial recorded adjustments and safe access between formats. Include consumable replenishment, fault recovery and the first acceptable case after restored settings.
Record incomplete opening, closure or transfer failures separately. Agree handling, recovery, retained evidence and acceptance results before sign-off.